• Gold Bar Mining Project

The Gold Bar Project is a hot dip galvanized Welded Wire Wall constructed in May 2018. The wall is located 15 miles from Eureka, Eureka County, Nevada. The designer of the wall was Jepsen Engineering.

WALL GEOMETRY:
•    Welded Wire Wall 
•    Maximum Wall Height of 26’
•    Maximum Mat Length of 20’
•    Seismic acceleration of 0.20g
•    20-year design life – Hot Dip Galvanized
•    2,688 SF
 

Wall Type: 
Welded Wire Wall
Wire Type: 
Galvanized
Owner Type: 
Mining
Wall Height: 
Wall Size: 
Under 5000 SF